Informationen über unsere Baukosten.

Aktuelle Schritte

Mädchen – Wohngebäude   26.028,00  €
Materialkosten 18.238,00  €
Transport 380,00  €
Hadwerkerkosten 7.410,00  €

Im Einzelnen:
(in Kenia Shilling)

Material Quantity   Price per Amount
Setting out (Tape, Sisal, Wire) 3.000
Balast + mix 3/4″, 1/8″ 100 t 1.200 120.000
Sand (River) 90 t 1.000 90.000
Cement 450 pc 665 299.250
Blocks Grade 2 (Machine cut – 200mm) 8.000 pc 51 408.000
Blocks for Toilets (150mm) 600 pc 25 15.000
Reinforcement Y12 40 pc 1.200 48.000
Reinforcement Y10 40 pc 950 38.000
Reinforcement Y8 72 pc 700 50.400
BRC No. A142 5 roll 4.000 20.000
DPC 200mm wide 216 m 100 21.600
DPM 500 gauge 100 m 100 10.000
Ordinary nails 45 kg 150 6.750
Roofing nails 30 kg 190 5.700
Hoop Irons 20 kg 150 3.000
3M Gauge 30 dumu mabati 240 pc 900 216.000
2.5M Gauge 30 dumu mabati 60 pc 700 42.000
Ridge Cap Gauge 30 m 600 18.000
Timber 4×2″ 420 m 160 67.200
Timber 3×2″ 308 m 75 23.100
Timber 2×2″ 108 m 75 8.100
Timber 8×1″ 60 m 230 13.800
Windows 1600×1200 24 pc 7.000 168.000
Windows 1200x 1200 5 pc 6.000 30.000
Windows 600 x 600 12 pc 3.000 36.000
Doors  1200 x  2100 8 pc 5.500 44.000
Doors 900 x 2100 3 pc 5.000 15.000
Doors 800 x 2100 13 pc 4.500 58.500
Plastic paint 20 litres 10 bct 3.000 30.000
Oil  paint 5 litre 12 bct 1.000 12.000
4” Painting  brushes 10 pc 300 3.000
6” Painting   brushes 10 pc 350 3.500
2” Painting  brushes 10 pc 250 2.500
Turpentine 20 l 200 4.000
2 lever mortise lock 24 pc 2.500 60.000
Barrel bolts 32 pc 300 9.600
Pull handle 24 pc 50 1.200
Engagement lock 13 pc 150 1.950
Labour
Excavation works, setting out and backfilling & cleaning 92.000
Concrete works for foundation walling 75.000
Construction of foundation wall 82.290
Foundation dpc Nil
Floor slab concrete works,laying of BRC,DPM,flooring,
Screed finish
113.000
Walling 200mm above ground to lintel and
150mm partion walling
180.000
Roof work timber works including lintel concrete
Trusses, Beams, Roofing covering
83.000
Plaster works 60.000
Paint  works 60.000
DOORS 23.000
WINDOWS 46.800

__________________________________________________________________________

Was schon hinter uns liegt   16.249,93  €
Toiletten- und Duschhaus  3.343,36 €
Hühner- und Ziegenställe
Gelände Einzäunen
Küche 443,90 €
Klassenzimmer 7.519,20 €
Schattenunterstand 276,68 €
Wasseranschluß ans Grundstück   437,72 €
Architekt, Baupläne & Genehmigungen (Stand 03/2012)  1.926,40  €
Landbereinigung (Stand 03/2012)  317,10  €
Grundstück 1.256,00  €
Anwaltskosten, Registrierung & Steuern 729,57  €